Nov 2000 Magnet bridges assembled and tested in DESY hall 2 |
![]() |
|
![]() |
|
![]() |
28.11.2000 New magnet bridges with normal conducting quadrupole magnets GI, GJ delivered to hall north |
![]() |
Completed with vacuum pumps, water cooling tubes and survey points |
![]() |
|
![]() |
Bridge for North Right (-z) parked in the hall for one night |
![]() |
Magnet support in front of Forward Muon Toroid |
![]() |
|
![]() |
|
![]() |
Support for NR bridge |
![]() |
29.11.2000 Insertion of the NR bridge by crane |
![]() |
Fine adjustments |
![]() |
|
![]() |
|
![]() |
|
![]() |
Pushing and pulling from both ends |
![]() |
|
![]() |
It's done! |
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
Moving support for NL magnet bridge |
![]() |
|
![]() |
|
![]() |
Thu 30.11.2000 Magnet bridge NL is installed |
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
Tue 6.12.00 Ortstermin machine and survey group |
![]() |
|
![]() |
Both bridges installed |
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
ABS2 with ion getter pump NR6.0 between GI1 and GI2 |
![]() |
ABS2 |
![]() |
Bellow between GI1 and ABS2 |
![]() |
GI1 and ABS2
Black light guides and PM box for ETAG-6 |
![]() |
|
![]() |
ETAG-6 fibers connected to PM box |
![]() |
Veto Wall |
![]() |
|
![]() |
Veto wall at -6m
Counter raised for access |
![]() |
|
![]() |
ABS3 between GI2 and GJ and IGP NR8.3
March 2002 |
![]() |
ABS3 |
![]() |
ABS3 |
![]() |
ABS3 |
![]() |
View towards IP:
GJ, IGP NR8.3, GI2, Veto wall (lowered) |
![]() |
View from tunnel NR towards IP:
GM, ABS4, GJ, Veto wall |
![]() |
|
![]() |
|
![]() |
ABS4 |
![]() |
|
![]() |
|
![]() |
Oct 2002
ABS3 |
![]() |
IGP NR8.3 wraped in Alu foil for heating |
![]() |
|
![]() |
|
![]() |
ABS3 and IGP NR8.3 |
![]() |
ABS2 between GI1 and GI2.
IGP NR6.0 wrapped in Alu foil for heating. |
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
Nov 2002.
GI1 on right side with North shell closed. |
![]() |
|
![]() |
|
![]() |
6.11.2002
BTS scintillator at -6 m installed. |
![]() |
2 scintillators from old small veto, 1 mm lead.
Mounted ring inward from above. IP is towards right. |
![]() |
PMTs |
![]() |
BTS next to ABS2. |
![]() |
|
![]() |
GI1 magnet and 6m BTS.
IP is towards left. |
![]() |
BTS at -8.3m. |
![]() |
2 scintillators, separated by 2x1 mm lead. |
![]() |
Mounted ring inwards at ABS3. |