April 2000 at Daresbury New 8-wire planar chamber completed at Daresbury Lab, UK |
![]() |
End view detail |
![]() |
Tim Greenshaw (Liverpool U) and Graham Houghton (Daresbury Lab) with new chamber #2 |
![]() |
October 2000 at DESY Hall 41 3 supermodules separated in clean room |
![]() |
SM 0 on assembly and survey table |
![]() |
SM 0 with 2 new and 3 old planars The GO magnet fits in here |
![]() |
6.12.00
3 Supermodules back together again |
![]() |
|
![]() |
a happy crew |
![]() |
14.12.00
FTD out of clean room in PETRA hall 41 |
![]() |
|
![]() |
|
![]() |
preamps added |
![]() |
Feb. 2001 Fully cabled |
![]() |
|
![]() |
FTi2 scintillators an PM tubes added |
![]() |
21.2.2001 Loading onto truck for transport from PETRA SE Hall 41 to Hall North |
![]() |
Don Clarke taking pictures... |
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
21.2.2001 Lifting through Hall North |
![]() |
Meanwhile, the CTD was parked under the ceiling |
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
26.2.01 Temporarily insert FTD into Cryostat to remove green frame |
![]() |
|
![]() |
FIT almost forgotten |
![]() |
FIT rescue meeting |
![]() |
Lay FTD cables over CTD |
![]() |
|
![]() |
|
![]() |
|
![]() |
View from inside cryostat FTD with FTi-2 |
![]() |
|
![]() |
|
![]() |
FTi-2 has 2 overlapping rings, in front and behind CFK support plate |
![]() |
Sat, 10.3.2001 FiT added in front of FTi-2 |
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
Connection of FTD with CTD |
![]() |
|
![]() |
GO support sandwiched between FTD and CTD |
![]() |
|
![]() |
|
![]() |
FTD cables neatly placed over CTD |
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
15.3.2001 Trackers inserted into LAr cryostat |
![]() |
|
![]() |